A Concelex-led joint venture has been named winner of the tender to design and build the Gura Humorului bypass in Suceava County, with a contract estimated at almost 598 million lei.

This item was produced with AI assistance under the editorial responsibility of Haydamax OÜ.

A joint venture led by Concelex has been named the winner of the tender to design and build the bypass road around Gura Humorului, in Suceava County, northeastern Romania, according to information obtained by Economedia from sources close to the project. Seven joint ventures submitted bids, and the estimated value of the contract is almost 598 million lei.

Suceava County Council president Gheorghe Șoldan announced on Wednesday that the evaluation of the offers had been completed and a winner selected, without naming the contractor. In his statement he said that 132 economic operators were involved, that a legal period for challenges would follow, and that the contract would then be signed. He added that from 2027 the county would open one of the largest construction sites in its history.

According to data from the SEAP public procurement system, the bidding groups were led by Automagistral-Pivden, Dimex-2000 Company, Construcții Erbașu, Drum Asfalt, Concelex, Geiger Transilvania and Străzi Concept. Concelex's group included Bitumina GmbH of Bulgaria, Patstroy VDH and X-Way Infrastructure. The other groups were built around a range of Romanian partners and, in the case of Drum Asfalt, the Turkish firms Ilgaz Insaat Ticaret Anonim Sirketi and Ilgaz Construction.

The tender covers Stage 1 of the bypass, built in a so-called Half-Profile configuration, meaning a single traffic lane in each direction is not included at this stage; instead one carriageway is built, in technical category III. The estimated value of the contract is 597.53 million lei and the planned duration is 25 months. The project was divided into two stages after costs and implementation conditions were reassessed, in light of higher initial cost estimates and the geopolitical situation.

Stage 1 will include the complete left-hand carriageway, the associated road signage, acceleration and deceleration lanes at future junctions, the substructure for embankments in both directions, earth ditches and culverts. The contract also covers the design and construction of the infrastructure and ducting for an Intelligent Transport Systems network, but not the ITS equipment itself, which is scheduled for the second stage together with the installation of the system.

The route is intended to take east-west transit traffic out of the town centre and to connect with the DN17 (E576) and DN2E roads, reducing road traffic inside Gura Humorului. It branches off the planned Baia Mare to Suceava expressway near the village of Frasin, where a junction with DN17 will be built. Near Sticleți the road will cross the Moldova river on a bridge, then pass over DJ177D on a viaduct, cross the Moldova again near the ski slope and Ariniș park, and cross the Humor river before reaching the south of the town, close to a former landfill that has been remediated. The bypass will rejoin the planned route of the Baia Mare to Suceava expressway, and a junction will be built to direct traffic towards Păltinoasa onto the existing roundabout at the DN17 and DN2E intersection.

The investment is financed through the 2021–2027 Transport Programme, using European non-reimbursable funds and money from the state budget via the Ministry of Transport and Infrastructure. The project's technical and economic indicators were reapproved through Government Decision no. 1074/2025, following the initial approval in 2024.