The machine that will bore the Poiana tunnel on the Sibiu–Pitești motorway in Romania is close to being fully assembled, with only one oversized transport still to reach the site. The Craiova Regional Directorate for Roads and Bridges (DRDP Craiova) announced the progress, describing the tunnel boring machine, nicknamed the «mole», as taking shape piece by piece.
The final component is the main part of the machine. It is due to arrive once most of the other parts have already been installed. More than 100 transports are required to bring the full equipment to the site, and assembly is expected to take three months. The last stretch of the route ran along an unpaved road in the Poiana area, after the convoy had crossed sections of motorway, national roads and county roads. DRDP Craiova has not yet given an estimated date for the start of the actual boring.
The Poiana tunnel will be roughly 1,780 metres long and will be the longest tunnel on the Sibiu–Pitești motorway. It forms part of Section 3, Cornetu–Tigveni, which measures 37.4 kilometres in total and is being built by the Webuild–Tancrad joint venture. The boring will be carried out with a tunnel boring machine, a technology that excavates the ground while lining the tunnel as the machine advances. According to DRDP Craiova, at its deepest point the bore will run about 120 metres below ground level. It is the first road tunnel on a motorway in Romania to be built with this method.
The cutting head was the first component to reach the site, and the remaining parts are being delivered in stages. The machine can only begin work once assembly is complete. The three-month period cited by the authority refers to assembly after all necessary components have been delivered, not to the duration of the boring itself.
Progress on the wider Cornetu–Tigveni section stood at 18.89 per cent physical completion at the beginning of October, according to the latest figures published by the National Company for Road Infrastructure (CNAIR). The contract is worth 5.32 billion lei excluding VAT and is financed through the Transport Programme. Besides the tunnel, the section includes two road junctions and 55 structures.
The contractual deadline for completing the section is November 2027, but the 45 months of execution are counted from the date the building permit is issued. The first permit for this lot was issued in December 2024, which pushes the estimated opening of traffic to 2028. Meanwhile, the mountain sections Boița–Cornetu and Cornetu–Tigveni are affected by a review of the environmental agreement, which is needed before the remaining building permits can be issued and works can be extended along the entire mountain route.
The Sibiu–Pitești motorway is one of the most important road links under construction in Romania. It is intended to connect the motorway network in the south of the country with the European corridor crossing the Carpathians, making the pace of works on difficult terrain such as the Poiana tunnel closely watched.